Write For Us

Govt spent RM273m for a new customs system - it was never completed

E-Commerce Solutions SEO Solutions Marketing Solutions
60 Views
Published
The government had paid out almost RM273 million for a new customs system that was never delivered.

However, in the end, the project failed to be completed, with only 27.2 percent of deliverables delivered.

According to the Auditor-General's 2019 report Series 2 - the uCustoms system project was initiated in 2013 and was supposed to complete in 2015.
Category
TV Saluran - TV Channel
Tags
kinitv, malaysia, politics
Sign in or sign up to post comments.
Be the first to comment